West Pier exclusion Zone

To whom it may concern:
I would be most grateful if you could make aware your boat drivers, club members, and any pleasure craft operating from your base of the Marine Exclusion Zone MEZ surrounding the former West Pier site in Brighton.
The i360 will be landing a 65m pontoon on the beach – held by tug in order to deliver the “Cans” for the construction of the development. In order to maintain a safe and sterile working environment a Maritime Exclusion Zone MEZ has been agreed with the local authority. This extends to 400m offshore / 50m West of the Pier substructure & 215m East. (see attached)
Dates for engineering work to be carried out are:
Week One: Wednesday June 10th time tbc to lay mooring lines and prep the area.
Thursday June 11th, Friday June 12th [approx 5am onwards] with a contingency day on Saturday June 13th
THEN:
Week Two: Monday June 22nd time tbc to lay mooring lines and prep the area.
Tuesday June 23rd, Wednesday June 24th approx 5am onwards with a contingency day of Thursday 25th June

I would be greatfull if you could circulate the attached to anyone you feel would benefit a personal copy.

Many thanks
Dave Samuel
consultant water safety, on behalf of I360 / Hollandia
Beach Landings